Q31. To what extent does your Program Executive Officer (PEO), Service Acquisition Executive (SAE), or other oversight officials request information about the following performance metrics?

  Very great extent
(percent)
Great extent
(percent)
Moderate extent
(percent)
Some extent
(percent)
Little or no extent
(percent)
Not applicable
(percent)
Number
of respondents
a. Earned Value 27.0 31.7 20.6 8.7 5.6 6.3 126
b. Program Master Schedule 24.6 35.7 23.0 11.1 4.0 1.6 126
c. Progress in implementing test plan 10.3 26.2 23.8 15.9 13.5 10.3 126
d. Technology Readiness Levels 4.8 18.3 24.6 15.9 25.4 11.1 126
e. Percentage of design drawings completed 2.4 8.8 12.8 19.2 37.6 19.2 125
f. Percentage of production processes under statistical control 5.6 8.1 15.3 14.5 30.6 25.8 124
g. Tracking funding obligations 55.6 33.3 7.1 0.8 1.6 1.6 126
h. Percentage of fielding or implementation 14.3 26.2 18.3 14.3 7.1 19.8 126
i. Progress made towards milestone criteria 35.7 30.2 13.5 6.3 6.3 7.9 126