Q33. To what extent is each of the following factors included in your performance evaluation as a program manager?

  Very great extent
(percent)
Great extent
(percent)
Moderate extent
(percent)
Some extent
(percent)
Little or no extent
(percent)
Not applicable
(percent)
Number
of respondents
a. Developing program requirements 4.0 20.6 22.2 18.3 28.6 6.3 126
b. Managing changing requirements 26.4 38.4 16.8 8.0 7.2 3.2 125
c. Executing funding for your program 45.2 37.3 7.9 5.6 2.4 1.6 126
d. Managing program technology risk 24.6 33.3 17.5 12.7 9.5 2.4 126
e. Testing requirements 16.7 26.2 22.2 17.5 11.1 6.3 126
f. Developing Request for Proposals (RFPs) 15.2 24.8 22.4 14.4 19.2 4.0 125
g. Selecting contractor sources 11.1 15.9 18.3 19.0 23.8 11.9 126
h. Administering contracts 17.2 33.6 22.1 13.9 11.5 1.6 122
i. Systems engineering 17.5 36.5 27.8 9.5 7.1 1.6 126
j. Delivering your program on budget 55.6 34.9 4.0 3.2 0.8 1.6 126
k. Delivering your program on schedule 58.7 32.5 3.2 2.4 1.6 1.6 126
l. Attaining performance objectives 42.1 47.6 5.6 1.6 1.6 1.6 126
m. Developing the Approved Program Baseline (APB) 13.5 31.0 30.2 9.5 8.7 7.1 126
n. Creating a collaborative environment among stakeholders 29.4 38.1 18.3 8.7 4.0 1.6 126
o. Representing your program to lead service and/or joint staff 23.2 40.0 19.2 8.0 8.0 1.6 125