Q39. Why was your program re-baselined? (Number of Respondents=63)

Category Number of Responses Percent of Respondents
Cost growth 22 35.0%
Schedule slips 19 30.2%
Funding cust/delays 17 27.0%
Requirements changes 11 17.5%
Procurement quantity changes 4 6.3%