Q9. To what extent do any of the following reasons explain why your entity did not use all of its funding commitments in funding years 2004, 2005, or 2006? |
d. My entity encountered unexpected problems in implementing internal connection projects, such as retrofitting, electrical rewiring, or construction. |
Question choices |
||||||||
---|---|---|---|---|---|---|---|---|
Major reason | Minor reason | Not a reason | Unable to judge | |||||
Type | Estimated percentage |
95 percent confidence interval |
Estimated percentage |
95 percent confidence interval |
Estimated percentage |
95 percent confidence interval |
Estimated percentage |
95 percent confidence interval |
1. All respondents | 3.7 | 1.4-7.8 | 4.1 | 1.7-8.1 | 86.4 | 80.2-91.3 | 5.8 | 2.8-10.7 |
2. Rural | 0.1 | 0.0-0.5 | 5.7 | 1.8-13.0 | 88.6 | 79.5-94.6 | 5.6 | 1.7-13.2 |
3. Urban | 6.5 | 2.3-13.8 | 2.8 | 0.5-8.6 | 84.7 | 75.3-91.6 | 6.0 | 2.0-13.4 |
4. Priority 1 funding only | 2.7 | 0.6-7.7 | 2.7 | 0.6-7.5 | 87.4 | 79.8-92.9 | 7.2 | 3.2-13.7 |
5. At least some priority 2 funding | 6.3 | 1.3-17.6 | 8.1 | 2.4-18.7 | 83.6 | 70.7-92.4 | 2.0 | 0.3-6.7 |
6. School district | 2.9 | 0.6-8.0 | 5.0 | 1.8-10.7 | 86.6 | 78.7-92.3 | 5.6 | 2.1-11.7 |
7. Library | 1.0 | 0.2-3.3 | 4.3 | 1.7-8.9 | 86.8 | 63.4-97.7 | 7.9 | 0.2-37.0 |
8. School | 7.4 | 1.3-21.5 | 0.9 | 0.1-3.1 | 85.8 | 70.6-95.0 | 5.9 | 1.0-18.1 |